Hide AdThe construction effort has been impressive; a huge undertaking which has seen 36,700 square metres of carriageway laid to relieve 90% of Broughton Village traffic from the A6.
Noise considerations have been addressed, with 1,016m of sound barriers, and even the humble newt has been looked after with 1.5km of permanent amphibian fencing.
Talking of nature, seven new ponds have been created for wildlife habitats, while more that 100 new trees have been planted in the immediate area.
Other road facts include:
• 5,700 square metres of footway surfacing
• 5,500m of stockproof fencing
• 6,700m of drains, 9,300m of kerbing and 1,860m of edgings
More than 22,000 vehicles which previously travelled along the A6 through Broughton every day will now use the new road, relieving many commuter headaches.
Broughton Bypass timeline
1970-76
Advertisement
Hide AdAdvertisement
Hide AdConcerns first raised about increasing congestion in Broughton village.
1986
Campaign to build a bypass to take traffic around the village is launched.
1991
Public consultation begins on two proposed routes for a bypass. Route B, roughly today’s layout, is chosen.
1997
An air quality and noise assessment indentifies problems around Broughton.
2001
LCC give planning green light to a revised bypass scheme.
2012
Advertisement
Hide AdAdvertisement
Hide AdPollution results in parts of the A6 lead to Broughton being designated an Air Quality Management Area.
2013
Scheme wins City Deal funding and is given priority.
2014
Scheme gets Growth Fund allocation.
2015
April - six day public inquiry.
July - Go-ahead from government.
December - Hochtief (UK) Ltd win contract.
2016
January - work begins with spring 2017 end date proposed.
September - end date revised to August 2017.
2017
July - new delays push opening back to early 2018.
September - opening brought forward to today.